As a user, I expect a consistent representation of the event status

    Details

    • Type: Bug
    • Status: Resolved
    • Priority: Minor
    • Resolution: Fixed and reviewed
    • Affects versions: 5.0
    • Fix versions: 6.0
    • Labels:
      None
    • Severity:
      Usability Issue
    • Steps to reproduce:
      Hide
      Steps to reproduce:
      1. Select a number of events
      2. Open Events->Actions->Start Tasks
       
       Actual Results:
      The table on the first page of the "Start Task" wizard shows a column with title "PROGRESS" and values like "SCHEDULED", "ARCHIVED", "WORFKLOW".
       
       
      Expected Results:
      That column should be labeled "Status" (it is the event status as reported in the Events table in the columns "Status"). It should display the same values as Events->col(Status).
       
       Workaround (if any):
       





      Show
      Steps to reproduce: 1. Select a number of events 2. Open Events->Actions->Start Tasks    Actual Results: The table on the first page of the "Start Task" wizard shows a column with title "PROGRESS" and values like "SCHEDULED", "ARCHIVED", "WORFKLOW".     Expected Results: That column should be labeled "Status" (it is the event status as reported in the Events table in the columns "Status"). It should display the same values as Events->col(Status).    Workaround (if any):  

      TestRail: Results

        Attachments

          Issue links

            Activity

              People

              • Assignee:
                Unassigned
                Reporter:
                staubesv Sven Stauber
              • Watchers:
                1 Start watching this issue

                Dates

                • Created:
                  Updated:
                  Resolved:

                  TestRail: Cases